IOG announces Saturn Banks production restart

27/11/2022

IOG provides a further Phase 1 operational update.

Saturn Banks Operations

  • Production has been restarted from both Blythe and Elgood into the Saturn Banks Pipeline System ("SBPS") as planned after completion of shutdown works
  • Gas sales are expected to recommence today following full repressurisation of the line
  • Final connection, dewatering and backgassing of the SBPS outer section to Southwark have all been successfully completed, bringing it up to pressure ahead of Southwark first gas
  • Additional modifications were also completed in parallel at Saturn Banks Reception Facilities onshore at Bacton terminal to de-risk potential for future shutdowns

Southwark Drilling

  • A2 hydraulic stimulation operations are underway and expected to continue into December
  • A2 first gas remains expected around year end, subject to stimulation progress and operational risks to final hook-up and commissioning
  • A1 well to be completed after A2 first gas, as previously confirmed

Rupert Newall, CEO of IOG, commented:
"I am very pleased to confirm that Saturn Banks Phase 1 production has been safely restarted after successful completion of shutdown activities. This was one of our top priorities as the new leadership team and the real commitment shown across the team to meet this key objective bodes well for our continuing work to address recent operational challenges.

In parallel, with hydraulic stimulation underway at the A2 well, we are equally focused on bringing Southwark onstream in a safe and timely manner, the next of a series of key objectives we have set to deliver the value in our portfolio. I look forward to keeping investors informed as these materialise."