Vestas secures 113 MW wind order in Japan

30/06/2021

Vestas has secured an order for the 113 MW Sumita Tono Wind Farm in Japan with Green Power Sumita Tono GK. With the site located in complex mountainous terrain in the Iwate prefecture, the order demonstrates how Vestas can leverage its industry-leading siting, project management and technology capabilities to deliver site-specific solutions in all conditions. 

Vestas has developed a customised tower solution for the project to accommodate the site’s challenging transport, wind and seismic load conditions, and it will feature the tallest hub heights for any wind turbines above 4 MW rating in the country, unlocking new wind resources at higher and more consistent wind speeds. Developed by Green Power Investment Corporation (GPI), the order will include supply and supervision of installation of 27 Vestas V117-4.2 MW turbines of which 23 will be installed on 114-meter towers and the other four on 94-meter towers.

It will be the first collaboration between Vestas and GPI, which is the Japanese partner of U.S based Pattern Energy Group LP that since 2004 has been focused on developing, constructing, and operating renewable projects in Japan. 

“We are pleased to partner with GPI with this landmark order in Japan,” said Purvin Patel, President and CEO of Vestas Asia Pacific, “With this order, we remain committed to contribute to Japan’s net zero goal and it also demonstrates our capabilities to tailor the best solution for our customers”.

“It is through the continued support and teamwork of various stakeholders and local government that the project was able to reach commencement of construction; a process in which Vestas played a vital role.” said Mitsuru Sakaki, President of GPI. “We would like to thank Vestas for this cooperation, on a particularly challenging project, and look forward to further long term collaboration to continue to push the Japanese wind industry to greater levels of efficiency and optimisation as we work to bring Japan’s sustainable energy targets closer”.

Vestas will also deliver a multi-year Active Output Management 5000 (AOM 5000) service agreement for the wind farm, providing an energy-based availability guarantee to ensure optimised performance and long-term business case certainty for the customer.

Delivery of the turbines will begin in the first quarter of 2022, with commissioning scheduled for the fourth quarter of 2022.