Site of UK’s first fusion energy plant

05/10/2022

West Burton power station site in Nottinghamshire has been selected as the home for the UK’s prototype fusion energy plant

The UK government has announced that the West Burton power station site in Nottinghamshire has been selected as the home for ‘STEP’ (Spherical Tokamak for Energy Production), the UK’s prototype fusion energy plant which aims to be built by 2040.

Fusion is based on the same physical reactions that power the sun and stars, and is the process by which 2 light atomic nuclei combine while releasing large amounts of energy. This technology has significant potential to deliver safe, sustainable, low carbon energy for future generations.

The government-backed STEP programme will create thousands of highly skilled jobs during construction and operations, as well as attracting other high tech industries to the region, and furthering the development of science and technology capabilities nationally.

The ambitious programme will also commit immediately to the development of apprenticeship schemes in the region, building on the success of the UK Atomic Energy Authority’s (UKAEA) Oxfordshire Advanced Skills centre in Culham. Conversations with local providers and employers have already begun, with schemes to start as soon as possible.

The UK government is providing £220 million of funding for the first phase of STEP, which will see the UK Atomic Energy Authority produce a concept design by 2024.

Image source: EUROfusion

Spherical Tokamak for Energy Production

STEP is a UKAEA programme that will demonstrate the ability to generate net electricity from fusion. It will also determine how the plant will be maintained through its operational life and prove the potential for the plant to produce its own fuel.  

The first phase of the programme is to produce a concept design by 2024. It will be a spherical tokamak, connected to the National Grid and producing net energy, although it is not expected to be a commercially operating plant at this stage.

The different phases of the STEP programme

Phase 1
The aim for this first phase of work is to produce a ‘concept design’ by 2024. This means an outline of the power plant, with a clear view on how we will design each of the major systems.  

Phase 2
Through phase 2 the design will be developed through detailed engineering design, while all consents and permissions to build the plant will be sought.

Phase 3
Construction of the prototype power plant will begin in phase 3, targeting completion around 2040.