Loxley Portland gas discovery Volumetric study confirms significant gas resource

21/09/2020

UK Oil & Gas announces that a report from Xodus Group details that the area of the Loxley Portland gas discovery lying within its 100% owned and operated PEDL234 licence, is interpreted to contain a significant mean case gross gas initially in place ('GIIP' i.e. gas in the ground before any future production) of 49 billion cubic feet ('bcf'). The portion of GIIP estimated to be recoverable to surface via any future production, the mean gross recoverable resource, is cited as 34 bcf, representing an estimated recovery factor of approximately 70%.

Reported high case net PEDL234 GIIP and estimated high case recoverable resources are 76 bcf and 54 bcf, respectively.

As shown in Tables 1 and 2 below, approximately 78% of the overall Loxley gas accumulation's gross mean GIIP and recoverable gas resource of 63 bcf and 44 bcf respectively, are interpreted to lie within the Company's PEDL234 acreage.

In terms of recoverable gas resources, the calculated figures places Loxley as one of the largest gas accumulations discovered and flow tested in the UK onshore. If proven by future production, the calculated gross mean recoverable resources would place Loxley second after the Saltfleetby gas field, the UK onshore's largest gas field to date, which produced approximately 73 bcf.

These results further underline the Company's view that the 48 km² Loxley geological structure contains materially significant gas volumes, which in a success case of around 4-5 bcf/year, on an energy equivalent basis, could have the capacity to power around 200,000 homes per year.

In the event that planning consent for the Company's appraisal and long-term testing programme is granted (see planning consent status below), and Covid-19 permitting, the Company seeks to drill the Loxley-1 well in the second half of 2021.

Table 1: Xodus calculated GIIP (bcf)

Loxley GIIP (bcf)

Low Case

Mid Case

MeanCase

High Case

UKOG Net PEDL234 Only

27

46

49

76

Total Loxley Accumulation

33

59

63

98

Table 2: Xodus calculated technically recoverable gas (bcf)

Loxley Recoverable Resource (bcf)

Low Case

Mid Case

MeanCase

High Case

UKOG Net PEDL234 Only

18

32

34

54

Total Loxley Accumulation

23

41

44

70


Loxley planning consent update

Following Surrey County Council's ('SCC') August 3rd decision to redetermine the Company's Loxley gas appraisal planning application, the Company understands that SCC are now working towards a rerun on 22 October, the first available planning committee meeting ('PCM') date.

The rerun decision was taken by SCC following receipt of external advice regarding the Company's and over 100 other formal complaints questioning the lawfulness of SCC's 29 June PCM. During this PCM the members voted by 6 to 5 against SCC's planning officer's recommendation to consent to UKOG's Loxley development.

A permit, covering all environmental aspects of the proposed development, was issued by the Environment Agency in June 2020.