Buru on commence major Canning Basin exploration drilling program

13/05/2021

 

  • Canning Basin exploration drilling campaign targeting a total 97 million barrels of conventional oil (mean prospective resources)1 on track for mid-June start
  • Drilling pad for first well (Kurrajong 1) nearing completion
  • First rig loads scheduled to leave Northern Territory on 24 May

Buru’s Executive Chairman Eric Streitberg commented:
“Drilling preparations are well under way and on track for our target mid-June spud. Site preparations have gone smoothly and without incident and we are very much looking forward to the spud of Kurrajong in just over 4 weeks.”

Background

Buru Energy is operating two major exploration wells in the Canning Basin this year, Kurrajong 1 and Rafael 1 in a 50/50 Joint Venture with Origin Energy. Buru will be carried by Origin for the first $16 million of the associated well costs. Kurrajong 1 is the first well to be drilled in the program and is located some 30 kilometers west of the Ungani Oilfield and is expected to have similar geology with mean prospective resources of some 29 million barrels of recoverable oil.

Kurrajong 1 site preparation

The drill site preparations for Kurrajong 1 are expected to be completed later this week.

The topsoil has been stripped and stacked ready for rehabilitation of the site with the ground works being supervised by senior Yawuru Traditional Owners. The site has been levelled and compacted, the cuttings sump formed up ready for installation of the impervious liner, and the 20 inch surface conductor and cellar has been installed.

All work on the site has been undertaken by local contractors who have completed the operations to a very high standard and incident free.

Drilling rig preparation

The drilling rig being used for the program is the Ensign 963, the sister rig to the Ensign 970 currently drilling in the Perth Basin. Ensign 963 is currently located at the Kyalla 1 Origin Energy wellsite in the Beetaloo Basin in the Northern Territory. Ensign and Buru have been undertaking rig preparation inspections and Ensign is currently on track to start mobilising the rig to the Kurrajong 1 well site,with the first loads expected to be picked up on 24 May.

It is expected to take two weeks to mobilise all the equipment to the Kurrajong site with rig up and rig inspection and acceptance expected to be completed in time for the target spud date of 15 June.